The Walnuts School – lighting for all hours

 

The Walnuts School in Milton Keynes is an all age community residential
special school and Childrens Home currently catering for 175 pupils from foundation
to year 14. All Pupils are on the autistic spectrum or have social communication
difficulties.

 

Background

As a school and home for many of the pupils our initial survey gleaned that the lighting was not fit for purpose.

Broken lighting caused unnecessary distress for pupils who are particularly sensitive to their environment.

Despite being a relatively new building the school had a number of inefficient fluorescent fittings which the estates team were struggling to find replacements as they were no longer produced.

A fully funded solution

Ineco Energy installed a fully funded lighting solution at The Walnut School. We planned to save the school money, improve the learning environment and reduce the school’s carbon footprint with our installation. The residential Walnuts School has complex lighting requirements compared to many traditional schools as it operates day and night, all year round.

Designing the lighting

We performed a detailed site survey before specifying a lighting solution to deliver the best learning and living environment for pupils and staff. We specified cooler colour temperature LEDs to help aid productivity and concentration in the classrooms, while warmer LEDs would encourage rest and relaxation in the bedrooms.

Installation

Our installation plan caused minimal disruption to the school day. The school building light installation took place outside of core school hours, once the children had gone home, while the home building lighting installation took place during daytime school hours.

Monitoring

Our ongoing monitoring measures the energy savings, which are better than expected and have delivered much needed financial savings to the school. A 5 year parts and labour warranty formed part of the installation package.

Results

Energy Savings

71%

Tonnes Carbon Savings

955

Financial Savings

£514,629

"As the Site Manager I thought I would have to write off 3 weeks of my life during the installation, Wow was I suprised! The whole process from survey/design, installation to completion was totally professional and stress free. The installation team were extremely accommodating and friendly, listening to us and working around the special needs of our school.

Site Manager, The Walnuts School